Master Invictus

Guide

A RACI matrix example for an IT project

27 November 2026

An IT example of a RACI matrix names the activities of a software change and one accountable person for each. The chart below is the example the RACI matrix builder loads. Suggestion lists for this phrase also include "raci matrix template for construction project". That is a different chart. This one is the information-technology example.

The five activities

Roles here are written in the cells, which is how the builder stores them. The letters are the usual ones: Responsible does the work, Accountable answers for it, Consulted is asked, Informed is told. The Wikipedia article on the responsibility assignment matrix defines them that way, and it notes that some project-management theories require exactly one accountable person per task.

ActivityResponsibleAccountableConsultedInformed
Write the requirementsBusiness analystProject managerSponsorTeam
Approve the scopeProject managerSponsorBusiness analystTeam
Build the interfaceDeveloperTech leadBusiness analystProject manager
Test the releaseTesterTest leadDeveloperProject manager
Decide go or no-goProject managerSponsorTech lead, Test leadTeam

"Decide go or no-go" has one Accountable name, the Sponsor. The Project manager does the work of getting the room to a decision, so that cell is Responsible, not a second Accountable. "Tech lead, Test lead" is two people in Consulted, because a comma splits the cell. The Team is Informed: they are told the result, and the row does not wait on them.

"Approve the scope" puts the Sponsor as the one Accountable and the Project manager as Responsible. The Business analyst is Consulted, which matches the first row, where that analyst does the writing and the Project manager answers for the requirements. The two rows are not copies of each other.

What the builder marks

Load the example on the builder and it fills these five rows. Change the names. Blank activities are dropped. The other rows stay in the order you entered them. A row with nobody Accountable, more than one Accountable, or nobody Responsible is kept, and the gap is named in those words. If the Sponsor and the Project manager were both typed in Accountable on "Decide go or no-go", the check would say "more than one Accountable". The row would stay. The builder would not average the two names and it would not delete the row.

Download CSV for Excel or Google Sheets, or Markdown for a wiki or a ticket. A cell that a spreadsheet would read as a formula gets a leading apostrophe in the CSV. How the letters sit in an Excel grid is in How to create a RACI chart in Excel. The same chart in an Excel workbook, beside a RAID log, a 5 by 5 heat map, action, decision and change logs, and a stakeholder register, is the RAID Log & Governance Kit.

What the builder records

Opening the builder sends a page view to this site. Building the matrix sends a product use when the chart is produced. A build that does not produce a chart does not send that event. Both go out as a beacon (POST /api/t) with the page address, the site that linked here, a campaign tag if the link had one, and a width class: under 640 pixels, under 1024, or wider. The beacon does not include the words you type. Scrolling records depth at 25, 50, 75 and 100 percent. A click records where it landed, as percentages, plus the element's tag, id or class, and not the text. If the browser sends Do Not Track or Global Privacy Control, the script stops before sending, and the server drops a beacon that still arrives with that signal. The privacy page is the full account.

All guides

Back to the home page