RAID log vs risk register: which one a project needs

29 November 2026

A risk register lists risks: things that have not happened yet and might. A RAID log lists risks too, and beside them the assumptions the plan rests on, the issues that have already happened, and the dependencies on work outside the team. A risk register is one of the four parts of a RAID log, kept in more depth.

What each one holds

The Wikipedia article on the risk register describes it as a repository for all identified risks, with more information about each one, such as the nature of the risk, its owner and the mitigation measures. That is the whole scope: risks, and what is being done about them.

RAID is four words. Some teams read the A as actions and the D as decisions. This page uses the reading the free builder uses:

  • Risk. It might happen. It has a likelihood and an impact.
  • Assumption. Something the plan treats as true without proof. If it turns out false, it becomes a risk or an issue.
  • Issue. It has happened. It needs an owner and a date.
  • Dependency. Something the project waits on that another team or supplier controls.

Side by side

Risk registerRAID log
RowsRisks onlyRisks, assumptions, issues, dependencies
Depth per riskMore: category, cause, trigger, response plan, residual ratingLess: a title, a rating, an owner, a response, a date
Typical readerA risk manager, an auditor, a governance boardThe project manager and the weekly status meeting
ReviewedOn a schedule, often monthlyWeekly, with the status report
What it missesIssues already open, and waits on other teamsThe depth a formal risk process asks for

Which one to keep

  1. A small or mid-sized project with one project manager: keep a RAID log. Four short lists in one place get read. Four separate files do not.
  2. A programme with a risk function, or a project that has to show a formal risk process to an auditor or a regulator: keep the risk register the organisation asks for, and a RAID log for the other three lists. Point the R rows at the register by id, so a risk is written once.
  3. If someone asks for both and nobody reads either, keep the RAID log and export the risk rows when the register is asked for.

The usual failure is the same in both. Rows are added at kick-off and never touched again. A row with no owner and no date is a note, not a managed item.

Starting one

The RAID log builder takes rows of all four types. Risks and issues get a likelihood and an impact from 1 to 5, and the rating is the two multiplied. It sorts open items first, then by type, then highest rating first, and gives each row an id such as R-01 or I-01. Download the result as CSV for Excel or Google Sheets, or as Markdown. Filter the Type column to Risk and you have the short form of a risk register.

The RAID Log & Governance Kit is the Excel version for a project that runs for months: the RAID log, a 5 by 5 heat map that counts the ratings entered, action, decision and change logs, a RACI, a stakeholder register and a lessons log. The heat map counts. It does not score a risk for you. There are no macros.

Related: RAID log vs decision log, action log and issue log.

What the builder records

Opening the builder sends a page view to this site. Building the log sends a product use when the log is produced. A build that does not produce a log does not send that event. Both go out as a beacon (POST /api/t) with the page address, the site that linked here, a campaign tag if the link had one, and a width class: under 640 pixels, under 1024, or wider. The beacon does not include the words you type. Scrolling records depth at 25, 50, 75 and 100 percent. A click records where it landed, as percentages, plus the element's tag, id or class, and not the text. If the browser sends Do Not Track or Global Privacy Control, the script stops before sending, and the server drops a beacon that still arrives with that signal. The privacy page is the full account.